The Sphere – Cladding Remediation Project

  • Client: Estates & Management
  • Services: •Project Management •Contract Administration •Cost Consultancy •Structural Engineering •Architectural

CapitalPCC were appointed to provide multidisciplinary consultancy support for the cladding remediation of The Sphere, a nine-storey higher-risk residential building in Canning Town. Our team are coordinating the design, cost and delivery strategy while progressing the scheme through the Building Safety Regulator Gateway 2 process.

Contract Value:
£15m (est.)
Programme:
96 weeks
Contracts:
JCT Design & Build Contract

Capital were appointed as the multi-disciplinary lead consultant to provide full professional services from inception to completion. Our services included Employers Agent, Fire Engineering, Cost Consultancy, Project Management, Structural Engineering, Architectural services, Contract Administration, Principal Designer & Clerks of Works. Due to the presence of an active Resident Association, we undertook a collaborative approach to the appointment of the PCSA contractor, including quality-based assessment criteria, as well as formal interviews with the steering committee.

 

Services

  • 01
    Project Management
  • 02
    Contract Administration
  • 03
    Cost Consultancy
  • 04
    Structural Engineering
  • 05
    Architectural

The project is being progressed through a two-stage Design & Build procurement route, with a Pre-Construction Services Agreement supporting site investigations, detailed Stage 4 design, cost and programme development ahead of the main construction contract. CapitalPCC are coordinating the contractor and wider consultant team, reviewing design information and progressing the scheme through the Building Safety Regulator Gateway 2 process.

Opening-up investigations identified additional wall types that had not been included within the original assessment, alongside limited existing structural information. This required further investigation and design development and resulted in changes to the anticipated scope, programme and cost. CapitalPCC coordinated the supporting technical information and revised cost submissions required to demonstrate the additional remediation need, ultimately securing approval for the revised funding position and enabling the project to progress.

Resident access has also required careful coordination, as intrusive investigations are needed within occupied apartments. CapitalPCC have supported early communication with residents and worked through the building management team to coordinate access and minimise disruption. The project remains on track towards its Gateway 2 submission in January 2027, after which the construction contract, final cost and funding will be agreed ahead of the planned remediation works.

Key Contacts

Richard O’Reilly
MRICS MFPWS RMaPS

Managing Director

richard@capitalpcc.co.uk

This has been a complex and challenging project, requiring significant investigation, design development and funding justification as new remediation requirements emerged. Through close collaboration with the client, consultant team and contractor, we successfully secured approval for additional funding and maintained progress towards the Building Safety Regulator Gateway 2 submission. We are proud of the progress achieved to date and remain committed to delivering the project through contract execution, construction and successful completion.

David Lawal Project Lead for Capital