Lancaster West Estate – LOT 1 External Works and Roofing

  • Client: Lancaster West Neighbourhood Team
  • Services: •Building & Safety Compliance •Design Management & Coordination •Programme and project planning •Façade & External Works

Capital PCC is delivering a major external refurbishment programme at Lancaster West Estate, improving fire safety, energy efficiency, and resident living conditions as part of RBKC’s wider regeneration strategy.

Contract Value:
£93m
Externals:
£74m
Roofing:
£19m
Duration:
Planned completion 2029
Capital PCC was appointed by the Lancaster West Neighbourhood Team (LWNT), acting on behalf of the Royal Borough of Kensington and Chelsea (RBKC), to lead a major external refurbishment programme across the Lancaster West Estate. This scheme forms a key element of RBKC’s wider regeneration strategy to enhance fire safety, energy efficiency, and resident wellbeing across its housing stock.
LOT 1 encompasses comprehensive renewal of the estate’s external fabric, including full roof replacement, installation of internal and external wall insulation (IWI/EWI), replacement of windows, doors, and fire exit doors (FEDs), AOV (Automatic Opening Vent) upgrades, and improvements to terraces, pergolas, and façades.
The works are being delivered in a live environment through a phased, resident-sensitive approach. Detailed planning, risk coordination, and stakeholder engagement have enabled the team to minimise disruption while maintaining programme pace and compliance with the Building Safety Act.

 

Services

  • 01
    Façade & External Works Consultancy
  • 02
    Building Safety & Compliance
  • 03
    Design Management & Coordination
  • 04
    Programme and project planning
The project has addressed the complexities of legacy construction and variable building conditions through close collaboration between architects, fire engineers, and RBKC. This coordinated approach has already achieved key milestones, including 100% completion of Barandon Walk’s roof ahead of schedule, with design development and scaffolding for Testerton Walk now underway.
To maintain transparency and build trust, Capital PCC has implemented structured reporting and visual progress tracking, ensuring both RBKC and residents receive regular updates on safety enhancements and key programme milestones.
This programme demonstrates how phased delivery, technical rigour, and stakeholder collaboration can transform occupied estates into safer, more sustainable communities. Lancaster West Estate is now positioned as a leading example of community-focused regeneration in London’s social housing sector.

 

Key Contacts

Richard O’Reilly
MRICS MFPWS RMaPS

Managing Director

richard@capitalpcc.co.uk
Anthony Michaelides
BSc (Hons) MRICS

Director of Building Surveying

Anthony.Michaelides@capitalpcc.co.uk

Our work on Lancaster West Estate demonstrates our ability to deliver high-value, complex refurbishment projects that enhance building safety, improve energy efficiency, and uplift the living environment for residents.

Anthony Michaelides Project Lead – Capital PCC

How can we help?

We pride ourselves on offering a personal service to each of our customers. Whatever your property requirements, please get in touch with us using the general enquiry form.