Vida House – Cladding Replacement Project

  • Client: London & Quadrant Housing Trust
  • Services: Design Development & Coordination, Employers Agent & Project Management, Contract Administration & Clerk of Works, Structural & Façade Engineering, Cost Consultancy & Principal Designer and Planning Permission
Capital were commissioned by Way of Life Management Ltd on behalf of WOL (London) LLP to manage the delivery for a cladding replacement scheme to Vida House Building.
Contract Value:
Circa £3m
Dates:
April 2021 to April 2023
Contracts:
JCT Design & Build Contract
Vida House is managed by Way of Life  is a residential development only a short walk away from Surrey Quays Overground station as well as Canada Water Underground station. Each of the 138 one and two-bedroom apartments on site have an open plan layout. Residents also have access to a secure car park and ample underground bike storage area. The building is understood to have been constructed in 2012 and has 5 storeys with the uppermost storey less than 18m above external ground level.

As the client requested a traditional procurement route, a Two Stage PCSA Design & Build procurement process was The project was tendered to selected specialist contractors  in Late April 2021. Capital Project Manager David Lawal lead an internal multi-disciplinary team comprising Structural Engineers, Cost Consultant, Architect, Contract Administrator, Principal Designer & Clerks of Works, with the support of our specialist Fire Engineer sub-consultant to deliver the scheme.

 

Services

  • 01
    Design Development & Coordination
  • 02
    Employers Agent & Project Management
  • 03
    Contract Administration & Clerk of Works
  • 04
    Structural & Façade Engineering
  • 05
    Cost Consultancy & Principal Designer
  • 06
    Planning Permission

Planning Permission was achieved via a full plans planning application submission and Building Regulation approval via an Approved Inspector.

As part of our role is to advise the client on the options available and the risk associated with the selected options for A1 or B1 rating. Cost and programme will be presented to the client for an internal appraisal for a decision. The development programme is for a start on site in April 2022 for a construction Phase duration of 50 weeks. The estimated contract sum is £3.5m for B1 rating increasing to circa £5m if A1 rating is to be achieved.

Key Contacts

Patrick Madigan
BSc (Hons) MRICS

Managing Director

patrick@capitalpcc.co.uk
Steve Davis
BScEng (hons) CEng MIStructE MSFE

Director of Structural Engineering

steve.davis@capitalpcc.co.uk

Capital were appointed as the multi-disciplinary consultant to provide; Employers Agents, Cost Consultants, Project Managers, Structural Engineers, Façade Engineers, Architects, Contract Administrators, Principal Designers & Clerks of Works services for this project

David Lawal Project Manager for Capital

How can we help?

We pride ourselves on offering a personal service to each of our customers. Whatever your property requirements, please get in touch with us using the general enquiry form.