Walbrook House – Stripping of Existing HPL Cladding

  • Client: London Borough of Enfield
  • Services: Architectural Services, Structural Engineering, Fire Compliance
Capital were appointed by Enfield Council to manage the Phase 1, stripping of the existing HPL cladding panels to Walbrook House and for providing an Option Appraisal Report in respect of the proposed design solution for reinstatement.
Contract Value:
£622,000
Dates:
April 2019 to July 2021
Contracts:
JCT Design & Build Contract
Capital acted as Design Coordinators, Structural Engineers, CA and Principal Designers for the Phase 1 project and were responsible for managing the initial opening up and investigation works, agreeing the method of stripping and temporarily waterproofing of the block and for management of the works on site.

In addition to the above we also carried out an Option Appraisal Report (for the Phase 2 reinstatement options) which set out the proposed design solution and costs for reinstatement. Procurement of the Phase 2 reinstatement works is currently being consider as part of a large scheme to the block for a new ground source heat pump heating installation and internal fire upgrade works.

The scheme came about following the Ministry of Housing, Communities & Local Governments advice to owners of residential buildings with respect to building safety. Enfield Council subsequently commissioned investigation works to all their blocks, including Walbrook House, to determine the fire performance of the cladding materials. This was in addition to other fire safety improvement works that were proposed to internal communal areas and common parts.

Services

  • 01
    Design Coordination
  • 02
    Contract Administration
  • 03
    Structural Engineering
  • 04
    Principal Designer
  • 05
    Option Appraisal Report

 

The results of the investigations established that the existing cladding panels to Walbrook House didn’t meet the current standards in respect of fire safety and other deficiencies were found. As such removal of the existing cladding panels was instructed by Enfield Council.

A specialist cladding contractor was appointed, and the method and extent of access and stripping was agreed through a series of design team meetings with the contractor and the design team. The block was made safe and fully stripped within 12 weeks. The Phase 2 reinstatement works are due to go on site this year.

 

 

 

 

 

 

Key Contacts

Patrick Madigan
BSc (Hons) MRICS

Managing Director

patrick@capitalpcc.co.uk

Once the Client had taken the decision to remove the existing cladding panels the timing of the removal needed to be immediate. This required careful consideration on the most appropriate procurement option to comply with the client’s standing orders, whilst ensuring the right special contractor was employed to undertake the works.

Patrick Madigan Project Director for Capital

How can we help?

We pride ourselves on offering a personal service to each of our customers. Whatever your property requirements, please get in touch with us using the general enquiry form.